Demo plans · Selective versus full · Not a laborer rate
Seattle demolition quantities are the hatches on the demo plans, and a laborer statistic is not a wrecking price
Demolition for a Seattle project is measured from the demolition plans and the notes that say what remains. SDCI is the city reviewer. The 2021 code cycle in effect since 15 March 2024 is context for permits, not a wrecking quantity. Full removal of a structure and a floor-by-floor gut are different scopes. The drawings say which one this is. A gut that leaves the frame is not priced as a cleared site.
Floor finishes over a slab that stays are finish removal, not structural demolition. Roofing tear-off is the roof area when the roof notes call for removal, and it is not the interior gut. Hazardous materials are excluded unless an abatement report is in the set and you ask for that scope to be listed. This page does not invent an abatement price.
There is no published occupation titled demolition contractor. The nearest construction occupation in the survey is Construction Laborers, $31.24 on OEUM004266000000047206103, Seattle-Tacoma-Bellevue. Using that number as a wrecking-crew rate would be wrong. It is cited so the gap is explicit. It is not a bid.
Shoring and underpinning of a neighbor are lengths and areas only when a shoring drawing shows them. Salvage the owner wants returned is a count from the specification, not a scrap credit. Temporary weather protection of a building that stays occupied is a means line only if you ask for it. Street use and a sidewalk closure are general requirements when the invitation describes them.
A Bellevue demolition sheet is not an SDCI sheet. Hillside access is left open unless the civil plan shows a road. Concrete saw-cutting is linear where the demo plan shows the cuts. Making those cuts up because the city is seismic is not done.
Elevator cabs, equipment pads, and rooftop units shown to be removed are counts. They are not buried in a building-area figure. Below-grade tanks are counts only when the demo or environmental sheets show them.
Upload the demolition plans and say whether abatement is in the request. Nobody visits the building to guess what remains.
A soft-story retrofit that removes only cripple walls is that length of wall, not a building demolition. Lead-painted components are called out as excluded unless the report quantifies them. A viaduct-adjacent scaffold is means, not debris.
A Seattle soft-story job that removes only a cripple wall is that length of wall, not a building teardown. Rooftop mechanical pads shown dashed for removal are counts. Lead-coated items stay excluded unless a report quantifies them. Interior slab removal where a new pit is cut is the pit area, and the rest of the slab stays.
Demolition quantities before treating a Seattle gut as a cleared site
Seattle demolition questions the plans have to split
Is a gut the same quantity as a full teardown?
No. The demolition plans say what stays. A remaining frame is not a cleared site.
Is $31.24 a wrecking rate?
No. File OEUM004266000000047206103 is Construction Laborers for Seattle-Tacoma-Bellevue. Demolition is not its own published line.
Do you include hazardous materials by default?
No. Abatement is listed only when a report is in the set and you ask for that scope.