Sample Constructability & RFI Audit Matrix
Cross-discipline drawing clashes, priority levels, and suggested contractor resolutions:
A drawing review identifies questions for the supplied documents. If you also need measured trade quantities, a priced bid and documented exclusions, review the commercial estimating package and deliverables and confirm that additional scope in your proposal.
Worked estimating example. Quantities show the stated scope and format; this is not a client project or a project-specific price quote.
| Drawing Discrepancy & Clash Description | Count | Severity Rating | Recommended Estimator Resolution | Estimator Note |
|---|---|---|---|---|
| Discrepancy 01 - Sheet M-201 vs S-102: 36x24 Supply Duct Clashes with W18x50 Beam | 1 | RFI | CRITICAL | Recommended Action: Request 4-inch duct transition or structural beam penetration sleeve |
| Discrepancy 02 - Sheet A-601 vs E-201: Sensor Flush Valves Missing 120V Circuit Feed | 36 | EA | MODERATE | Recommended Action: Add electrical branch homerun circuit to panel LP-2 |
| Discrepancy 03 - Sheet C-301 vs S-101: Civil Paving Thickness Excludes Slab Dowels | 1 | RFI | MODERATE | Recommended Action: Clarify concrete trade ownership for smooth joint dowel baskets |
| Discrepancy 04 - Sheet A-102: Fire-Rated Shaft Wall Lacks Specified Deflection Track | 420 | LF | CRITICAL | Recommended Action: Add slotted deflection track detail per UL design HW-D-0181 |
Scope and deliverables
Forensic Cross-Discipline Plan Review Services
Many construction disputes and budget overruns trace back to conflicts between architectural, structural, civil, and MEP drawings. Discovering that a main duct trunk clashes with a structural steel beam during preconstruction costs minutes to resolve with an RFI; discovering it on site halts entire crews and generates expensive change orders.
At F&K Estimatings, our multi-discipline estimators perform forensic plan reviews before you submit your bid. We overlay drawing sets, check detail references, and audit equipment schedules.
The agreed review can include a prioritized RFI log, conflict markups and a document-based constructability report. Delivery and revision coverage are confirmed after reviewing the drawing set and requested scope.
Scope, price, and delivery are confirmed after reviewing the project documents and requested deliverables.
Deliverables for your agreed scope
Clash and coordination log
MEP, structural, civil and architectural overlays checked for spatial conflicts, each logged with the sheet and detail where it appears.
Pre-bid RFI log
Structured questions with referenced sheet numbers and detail callouts, drafted so the answers protect pricing instead of opening new exposure.
Scope-gap reconciliation
Trade-package ownership lines drawn between concrete and earthwork, MEP and structure, so no scope is double-counted or dropped.
Code and constructability notes
Egress, accessibility, fire-rating and phasing observations tied to the drawings, plus value-engineering opportunities found during the review.
Who this service supports
- General Contractors
- Commercial Developers
- Design-Build Teams
- Trade Subcontractors
- Architects & Engineers
Plan Review: quantities, checks and quote requirements
A plan review checks the drawing set before you price it: missing sheets, conflicts between disciplines, unclear scope and items that are likely to become change orders.
Measurement and reporting basis
- Sheet and detail references
- RFI or clarification log with responsible party
- Scope or allowance impact of unresolved information
Documents to include
- Current drawing set and specifications
- Addenda issued to date
- Your scope of work if you are a subcontractor
Also identify the current revision, addenda, project ZIP code, requested trades and bid deadline.
A scope check before pricing
Log a drawing reference, the unresolved issue and the estimate consequence for each finding. Route conflicts to the contractor or design team for an RFI instead of silently redesigning an assembly.
Scope limits: Permit plan review, stamped design review and certification that every clash has been found are excluded.
Worked estimating example
Log a conflict instead of silently choosing a detail
If a plan tag calls for a 4-inch slab while the referenced section shows 6 inches, neither drawing instruction should disappear from the estimate record.
- What the estimate should record
- Record both sheet/detail references, the question for the design team and the provisional estimating basis. Flag the affected quantity until the response is incorporated.
- Resolve before pricing
- Which document takes precedence, and has the responsible designer issued a clarification?
Constructability review services for estimating scope and bid documents
Construction plan review identifies estimating questions in the issued drawings before quantities and costs are finalized. Our pre-bid plan review focuses on missing dimensions, schedule conflicts, trade interfaces and scope ownership so the project team can resolve them before pricing.
Drawing and schedule reconciliation
Requested output: A referenced list of discrepancies between plans, sections, schedules and specifications.
Confirm in your quote: Current issue, disciplines included, addenda and which documents take precedence.
Trade interface review
Requested output: Questions identifying who carries connections, openings, supports and shared work.
Confirm in your quote: Contract boundaries, owner-furnished equipment and subcontractor exclusions.
Estimate scope review
Requested output: An inclusion, exclusion and clarification log tied to the requested bid package.
Confirm in your quote: Existing estimate version, required cost codes and the decision the review must support.
This is an estimating document review. It does not certify constructability, engineering adequacy, code compliance, permitting or construction means and methods. The design team and contractor resolve the identified questions.
Request this estimating scopeUS project coverage for plan review
For US projects, include the ZIP code and the location-sensitive inputs below.
- Supply the issued project specifications, jurisdiction-related notes and addenda that affect the estimate scope.
- Identify location-dependent access or existing-condition questions for the clarification log; unresolved requirements need a documented estimating assumption.
The proposal records the pricing date, cost sources and unconfirmed allowances. Explore US service area information or send your project details for a scope quote.
Use the document checklist above to request quantities only, a priced estimate or a review of an existing bid.
Request a plan review scope quoteScope coverage for your bid package
Cross-Discipline Clash Detection
Overlaying MEP, structural, civil, and architectural drawings to flag physical spatial interferences.
Pre-Bid RFI Generation
Structured RFI logs with referenced sheet numbers, detail callouts, and suggested technical solutions.
Constructability & Phasing Audits
Evaluating site access constraints, crane staging, scaffolding logistics, and temporary shoring.
Scope-Gap & Double-Counting Reconciliation
Demarcating measured trade package ownership lines between concrete/earthwork, MEP/structural, and drywall/framing.
Building Code & Life-Safety Compliance
Verifying IBC egress widths, ADA accessibility clearances, fire-resistance ratings, and UL assembly details.
Value Engineering Opportunities
Identifying over-engineered details and practical material substitutions to optimize preconstruction budgets.
How your estimate is prepared
We start from the full drawing set, the specifications and the bid date. We overlay the disciplines, log the clashes and gaps, and return a written review with RFI drafts you can send before pricing closes. Our review method, from overlay to written findings, describes the review steps, software and version control behind each review.
Estimating fees and delivery
Plan-review fees turn on the size of the drawing set and how many disciplines need overlaying — a single-discipline check takes less estimating time than a full multi-discipline coordination review with an RFI log. The proposal you receive states the fee and the delivery date for the agreed review before work begins.
| Scope / project type | Typical delivery | Typical fee |
|---|---|---|
| Single-trade material takeoff | Typically 24–48 hours after approval | $150–$1,000 typical |
| Residential construction estimate | Typically 2–4 business days after approval | $400–$1,000 typical |
| Commercial preconstruction package | Typically 3–5 business days after approval | $150–$1,000 typical |
| Industrial & heavy civil takeoff | Typically 4–7 business days after approval | $1,000–$5,000+ typical |
| Ongoing estimating support | Priority queue agreed in writing | $1,800/mo typical |
Review fees cover the coordination work above. Sheet count, disciplines and bid date set the written proposal.
Frequently asked questions
What does a comprehensive construction plan review include?
Our plan review conducts a forensic cross-audit across architectural, structural, civil, mechanical, electrical, and plumbing (MEP) drawings. We identify drawing inconsistencies, dimensional clashes, missing details, constructability obstacles, and code compliance gaps before contracts are signed.
How do you identify spatial coordination issues between MEP and structural trades?
We perform multi-discipline plan overlays in Bluebeam Revu, mapping high-pressure duct runs against structural steel beam depths, verifying underground plumbing slope against footing grade beams, and checking electrical disconnects against mechanical equipment schedules.
Do you provide an itemized RFI log for pre-bid clarification?
Yes. Every plan review delivers a structured Pre-Bid RFI Matrix categorized by drawing sheet, CSI division, priority level (Critical, Moderate, Low), and recommended question wording ready to submit to the architect or owner.
Can plan reviews be performed on schematic design (SD) or 50% DD drawing sets?
Absolutely. Early-stage plan reviews during Schematic Design (SD) and Design Development (DD) provide the highest return on investment, allowing design teams to fix discrepancies before construction documents (CDs) are finalized.
What is your typical turnaround time for a complete plan review?
Delivery depends on the drawing set, requested trade scope, pricing requirements and bid deadline. The delivery date, scope and revision coverage are confirmed in the written quote after document review.