Painting section · Exterior elevations · No extra coat for rain
Seattle coating area comes from the painting section, and a wet climate does not add a coat the spec never named
Seattle coating quantities are square feet by substrate from the room schedule and from the elevations that actually receive a coating. SDCI does not set the number of coats. The painting section does. A long wet season neither adds a coat nor erases one the elevation still shows.
Gypsum, ceilings, door leaves, and frames can each carry a different product, so they are not one area. Lap siding, wood boards, and bare concrete are coated only where the elevation calls for a finish. Cladding that is already the finish is not painted unless the spec gives that surface to the painter.
Painters, Construction and Maintenance are filed at $30 an hour on OEUM004266000000047214103 for Seattle-Tacoma-Bellevue. The occupation name covers new work and later upkeep together, so it is a poor proxy for a new-building crew alone. It is not a price per square foot. The survey is wider than the city. A private interior does not inherit a public wage determination.
Preparation of an existing film is an area only when the spec defines the prep. A wash and a full strip are different scopes. New board with no old film does not get a repaint prep quantity. Intumescent on steel is measured in the unit that spec uses. Epoxy floors are only the rooms the spec names. Cedar that stays natural is not a paint area.
Stair enclosures stay as wall and soffit area. A lift is noted only when you ask for means. Sealant assigned to the painter is linear. Pavement marking stays on the civil sheet. Bellevue elevations are not painted into a Seattle total. The deliverable is the areas by substrate, the coat note from the spec, and the gaps.
Galvanized lintels the Seattle spec assigns to the painter are lengths, not wall area. Pipe stencils are a count of marks when a schedule lists them. Intumescent thickness is whatever that spec measures, kept off the latex wall total. A ferry-pier or pier-shed painting package is only the steel the painting section claims.
Coating areas before treating Seattle rain as an extra coat
Seattle coating bid questions
Do you add a coat because of the rain?
No. The number of coats follows the painting section. Weather is not a substitute for that section.
Is rainscreen cladding a paint area?
Only when the specification says the painter coats that cladding. Otherwise it stays with the wall assembly that buys it.
Is $30 a square-foot price?
No. OEUM004266000000047214103 is the hourly statistic for Painters, Construction and Maintenance.