Selective removal · Existing plans · Haul volume
Chicago demolition quantities are the hatched removals, not the age of the block
Demolition drawings in Chicago are usually an alteration, reviewed with the building permit by the Department of Buildings. Full removal of a structure and a floor-by-floor gut are different waste calculations and different protection details. Title 14B and, when the applicant has elected or been required to use them, the 2026 amendments in Memorandum 2026-001 frame the permit. They do not tell you how many dumpsters the hatch marks equal. Measure the hatched partitions, slabs, finishes, and equipment. “Remove all interior non-bearing walls” is quantifiable from the existing plan. “Gut the building” without a remaining-shell diagram is not.
Debris volume is computed from those assemblies. Shoring at a cut slab is included when the structural demo sheet details it. Winter temporary heat for an occupied neighbor is a means-and-methods cost you add only if the phasing says the work runs in freezing weather and you want that cost carried here. Asbestos and lead are a survey and a licensed abatement price. The year the building was built is not that survey. Saw-cut lengths are taken from the structural demo plan. Floor finishes over a slab that stays are a finish removal, not structural demolition. Equipment to remain is protected, not hauled. Salvage items the owner wants returned are a count from the spec, not a credit invented from scrap prices. Masonry rubble and gypsum debris can be listed as separate volumes when the haul spec requires sorting. If it does not, one mixed volume is labeled as mixed.
Construction Laborers in the Chicago-Naperville-Elgin area average $33.26 an hour on May 2025 series OEUM001698000000047206103. Demolition contractors are not an OEWS line of their own. Treating the laborer average as a wrecking price would misstate the crew. It is published here only so the gap is explicit. Public work uses the wage schedule in the invitation instead.
Existing plans and the demo sheets are the source. No floor is walked to see what a tenant left behind. Send both sets and the phasing notes. Shoring at a removed bay is counted from the structural demo sheet. Protection of an adjacent occupied tenant is a temporary-partition area when the limit line is drawn. Night-work premiums are a labor assumption you add if hours are restricted, not a debris quantity. Salvage the owner wants returned is a count from the specification, not a scrap credit. Mixed debris is labeled mixed when the haul spec does not require sorting. Masonry rubble can be its own volume when it does. Floor finishes over a slab that remains are finish removal, not structural demolition. Equipment tagged to stay is protection, not a haul load.
Demolition takeoff practice that is not limited to this city
Chicago demolition lines that should stay out of the gut number
Do you price abatement from the building’s age?
No. Abatement needs a survey. Age is not a quantity of asbestos or lead.
Is the laborer wage a demolition rate?
No. Series OEUM001698000000047206103 is Construction Laborers. It is cited because demolition is not a separate published occupation, and it is not a bid.
Are winter enclosures automatic?
No. Temporary heat and enclosures are listed when you say the occupied-adjacent work will run in freezing weather.