Existing plaster · New board · Spec systems
Philadelphia coating areas keep existing plaster separate from new gypsum
Coatings in a Philadelphia rehab usually land on plaster that stays, with new board only at the patches. Those substrates are separate areas. Licenses and Inspections does not pick the product. The painting specification does, inside the code edition that filing uses, including city amendments on current applications. When an approval names a historic exterior coating, that named product is the one measured.
Walls and ceilings are areas by system. Trim, frames, doors, and rails are counts or lengths. Where a survey or the spec calls for lead-safe handling, that condition is written beside the area. The year on the deed is not a survey, and it is not an extra coat. Stair-hall access equipment is included only when you put access in the painter’s number and the section gives a height.
Painters, Construction and Maintenance are published at $27.79 for Philadelphia-Camden-Wilmington on 2025 file OEUM003798000000047214103. The official title mixes jobsite painting with maintenance work, so it is a poor stand-in for a stair-tower crew and it is not a square-foot number.
Existing-film preparation is measured only after the spec says what “prepare” means. On an occupied house, a wash-down and a heavy scrape are different operations. An undefined prepare note stays open.
Upload the finish schedule, the painting section, and exterior elevations when the outside is in this bid.
Stair balusters are counts. Window stools and aprons are lengths. Radiator covers, if they stay and are painted, are counts. A mural or a sign panel is a count of panels, not wall area. Exterior cornice painting is a length or an area from the elevation that dimensions the cornice. An elevation that only says paint cornice, with no projection, is a gap. Porch ceilings underneath are an area when the elevation or the reflected plan shows them. Masking of finished floors is included only if you assign protection to the painter and the rooms are identified.
Balusters are piece counts. Stools and aprons are lengths. Radiator enclosures that remain and get coated are counts of enclosures. Cornice work is taken from an elevation that gives a projection. Without a projection the cornice line stays open. Porch ceilings, when shown, are their own soffit area. A painted sign band is a panel count. Protection of finished floors is included only in the rooms you assign to the painter. Stair landings are areas separate from the baluster count.
Coating areas before plaster-and-board splits
Philadelphia coating splits between old plaster and new board
Do you treat all old plaster as a full skim?
No. Skim and other prep are measured only when the specification defines them. An undefined prep note is a gap.
Are lead-safe costs automatic in an old rowhouse?
No. They are included when a survey or the spec requires them. Age alone is not a survey.
Is $27.79 per square foot?
No. File OEUM003798000000047214103 is an hourly mean for a broad painter occupation.