SFRM · UL designs · 2022 building volume
New York City fireproofing is measured member by member from the rating schedule
Sprayed fireproofing and intumescent coatings in the five boroughs are sized by the construction type and the hourly ratings in the code analysis, under the building volume the Department of Buildings is enforcing. For a current filing that is the 2022 New York City Building Code, effective 7 November 2022, on a 2015 IBC base with city amendments. The tested design on the specification, not a pounds-per-square-foot story about high-rises, sets thickness and product. A column schedule that names a UL design is a measurement instruction. A specification that only says “fireproof all steel” is incomplete, and the missing design goes on the exclusion list.
Measure surface area or board feet by member size: beams, columns, decks, and braces separately, because thickness and loss factors differ. Deck fireproofing is not beam fireproofing. Intumescent paint on architecturally exposed steel is a different product from cementitious spray and is priced only where the finish schedule or the spec calls it out. Patching after other trades is a quantity only if the bid form includes a patch allowance you can define. Firestopping at penetrations is a count or a length from the rated-wall schedule, and it is often a different subcontractor. Do not fold it into the spray tonnage.
Tower cores, transfer floors, and low-rise steel frames do not share a spray density. Exposed exterior steel that needs an exterior-rated product is a specification choice, not a borough rule. There is no May 2025 OEWS occupation that isolates fireproofing applicators, so this page does not borrow a painter’s or an insulator’s wage and pretend it is the spray crew. Labor rates, if you need them, have to come from your applicator or from a wage decision the contract actually attaches.
Metal deck fireproofing follows the deck type and the underside area, with flutes counted the way the design manual for that UL number describes, not as a flat plate. Beams that frame into a rated column pick up only the surface the design leaves exposed. Top-of-steel conditions under a concrete slab are often unrated and should not be sprayed “to be safe.” A roof dunnage frame for equipment is easy to leave out of the member list; it belongs in the takeoff when the structural plans show it and the spec does not exclude it. Masking of adjacent finishes, when the spec requires it, is an area of its own. Primers that are incompatible with the spray are a specification conflict to list, not a product substitution.
F&K does not inspect bond strength and does not climb the steel. Send the structural frame, the code sheet with construction type and ratings, the fireproofing specification, and any UL design sheets the architect already selected.
Fireproofing takeoff rules that apply beyond New York City
NYC fireproofing assumptions that should stay visible
Can fireproofing be estimated as a rate per building square foot?
Not from this desk. Member sizes and the UL thickness drive the quantity. A square-foot factor hides both.
Is firestopping included with the spray?
Only when you ask for it and the rated-wall and penetration schedules are in the set. Otherwise it is excluded so it is not double-sold by the spray contractor and the stopper.
Which wage should the estimate use for applicators?
There is no separate OEWS line for fireproofing applicators in the May 2025 metro table. Do not substitute a neighboring trade. Use your crew rates or the contract’s wage decision.