2023 NEC · 2021 IPC · 2021 IMC
Dallas mechanical, electrical, and plumbing quantities follow three different adoption dates
Development Services did not adopt one year for every trade. Plumbing is the 2021 International Plumbing Code and mechanical is the 2021 International Mechanical Code, both with Dallas amendments, effective 12 May 2023. Electrical is the 2023 National Electrical Code with Dallas amendments, effective 23 May 2025. A set that still cites an older electrical article against a 2021 plumbing spec needs that clash written down. Energy for the building is the 2021 energy code from the same May 2023 package. Equipment efficiency is read from the schedule and the energy notes together.
Keep the trades in separate blocks. A rooftop unit’s curb, its disconnect, and its condensate are three assignments. Duct weight is not conduit. Fixture counts are not device counts. Hail ratings on exterior equipment are included only when the specification names an impact rating. They are not a zip-code adder. The clay under the building does not change a panel schedule.
Three hourly means from the Dallas-Fort Worth-Arlington file, 2025 release, are not averaged. Electricians $28.83, OEUM001910000000047211103. Plumbers, Pipefitters, and Steamfitters $29.94, OEUM001910000000047215203. Heating, Air Conditioning, and Refrigeration Mechanics and Installers $29.69, OEUM001910000000049902103. Duct fabrication is another occupation. None of these is a bid. Private work does not inherit a public wage determination.
Alarm devices and fire sprinklers stay out until those specifications are in the request. Lighting is a fixture count from the lighting plan, not a wattage allowance.
Send the three disciplines and say whether alarm and sprinkler are included. No startup is performed.
A makeup-air unit serving a kitchen is a schedule line of its own, not part of the hood sheet metal. Standby generators appear only if the site electrical drawing is in the upload. Feeders are taken from the panel schedules. Where the riser diagram ends at the service, downstream feeders are omitted. Water heaters remain a plumbing item. Strip heat inside a unit is noted on that unit. Condensate ownership is written from the invitation. Silence on condensate is an open assignment, not a double count.
Luminaires come off the reflected ceiling plan as counts by type mark. A lighting-power density note does not become a fixture list. Alarm devices are omitted until that spec is part of the ask. Cable tray is measured where the plans actually show tray. Conduit for rooftop photovoltaics is included only along a drawn route. A blank note about future solar is left out. Water heaters do not move into the electrical block.
Systems quantities before the split Dallas adoption dates
Dallas systems dates that are easy to collapse
Did Dallas adopt the 2023 NEC for plumbing too?
No. Plumbing remains the 2021 IPC with Dallas amendments from 12 May 2023. The 2023 NEC, effective 23 May 2025, is the electrical book.
Can the three wages be averaged because they are close?
No. They are different occupations in the metro file. Closeness is not a reason to blend them.
Does a Dallas mailing address mean Development Services?
Only inside the city limits. Many “Dallas” addresses are other cities. The parcel decides.