2024 IBC and IRC · 2024 IECC · No TWIA county line
Austin roof areas follow the 2024 building book, and Travis County is not on the coastal windstorm list
Roof coverings inside Austin are reviewed by Austin Development Services under the 2024 International Building Code and the 2024 International Residential Code. Those local amendments took effect on 10 July 2025. Steep-slope residential area and low-slope commercial area are measured separately because they are different assemblies. They are not averaged into one square.
That same table adopts the 2024 International Energy Conservation Code. Insulation at the roof, a cover layer, and any taper are measured only where the roof plan or the energy sheets draw them. Summer heat does not invent an R-value. Fastener layouts are separated only when the specification draws the zones. If the specification never draws zones, the layout stays unresolved.
Travis County is not among the counties named for the Texas Department of Insurance designated catastrophe area. A TWIA windstorm certificate is not a Travis County line item. Design wind on the structural notes still controls clips and edge metal when those notes exist. The absence of a coastal certificate is not permission to ignore the edge metal the roof plan dimensions.
File OEUM001242000000047218103 lists Roofers at $24.08. Geography on the file is Austin-Round Rock-San Marcos, which is wider than the city limit. The figure is not a completed square and it is not a city crew number.
Coping along a parapet is linear. Overflow openings are each. Protection pads at walking paths are each. Curbs the mechanical contractor supplies are flagged so the roof package does not purchase that metal a second time. Curbs at skylights are each. The flashing that turns up a parapet is linear. Gutters are linear and the joints in them are each. Pedestal pavers sitting above the sheet are a separate area from the sheet itself.
An overnight tie-in while the old covering comes off is a means line only when you request it. Air terminals are counted only when this trade buys them. Equipment screens on the roof stay in metals until a note assigns the screen here.
Upload the roof plan, the specification, and the energy sheets if insulation is in this bid. No sample is removed from the existing covering.
A standing-seam metal roof and a single-ply membrane on the same building stay in separate areas, including their different edge conditions. Ridge vent and a powered rooftop fan are not both “ventilation.” The fan belongs to the mechanical schedule. Pipe boots are each, sized from the penetration schedule. A cricket that has no thickness is left unresolved rather than assigned a board-foot guess.
Roof areas before Austin’s 2024 code package
Austin roof items the climate does not insert
Does every Austin roof need a windstorm certificate?
Travis County is not on the TDI designated catastrophe list. Edge metal still follows the roof plan and the structural notes you send.
Will you add insulation because summers are hot?
No. Insulation and taper follow the roof plan and the energy sheets. A silent plan leaves those lines open.
Is $24.08 a square price?
No. File OEUM001242000000047218103 is the metro hourly figure for roofers, and it includes Round Rock and San Marcos.