Cooling schedule · Drawn duct · 2024 mechanical book
Phoenix air-side quantities are the scheduled cooling equipment and the drawn duct, not an added ton
Phoenix mechanical review at Planning & Development uses the 2024 mechanical model and the 2024 energy model adopted together on 1 August 2025. Efficiencies on the schedule have to be readable against the energy form. When they disagree, both are written down. The quantity is not edited to force a match. Afternoon design temperatures are already inside the engineer’s selection. Do not add capacity in the takeoff.
Duct is weight and surface from the drawn sizes, fittings counted, not a pound-per-foot guess. Rooftop units, split systems, and air handlers are schedule lines. Curbs and rails are counts. Condensate is a small piping system and may belong to the plumber. Say which contract holds it. Economizers and outside-air paths are included when the schedule or the diagram shows them. They are not assumed on every house.
Two wages, same metro release. Heating, Air Conditioning, and Refrigeration Mechanics and Installers: $29.91 hourly mean, May 2025 file OEUM003806000000049902103. Sheet Metal Workers: $27.59, file OEUM003806000000047221103. Using the mechanic figure for fabricated duct, or the sheet-metal figure for a chiller set, misstates the crew. Neither is a price per ton.
Send the plans, the schedule, and the mechanical specification. No balance is run and no roof is visited. Exhaust fans serving restrooms are counts from the fan schedule, separate from the rooftop cooling units. A note that says fan by others leaves that fan out of the air-side list.
Vibration isolation is a count per machine. It is not a percent of the equipment quote. Test and balance is its own line when the specification assigns it to this contractor. Controls and sequences stay out unless you asked for a controls count. Duct and pipe insulation are areas and lengths kept beside the metal weight. Balancing valves are counts where the diagram shows them. Roof rails for a screen around equipment are counts or lengths from the structural or mechanical detail, and they are not duct. Electric heat inside a unit is an accessory note.
Outside-air louvers are counts or areas from the elevation, coordinated with the opening schedule so the same louver is not also a window. Smoke and fire dampers are counts from the damper schedule. Flexible connections at equipment are counts. Refrigerant line sets are lengths by size when the diagram dimensions them. A diagram that only says line set by installer is a gap. Condensate neutralizers, if specified for condensing equipment, are counts. Roof curbs that are structural steel are flagged so they are not also in the mechanical pounds.
Air-side quantities before the Valley cooling schedules
Phoenix air-side additions that are not real
Do you increase tonnage because of Valley heat?
No. The schedule is the equipment list. Heat is why the engineer sized it. The takeoff does not resize it.
Who owns condensate?
Whoever the invitation assigns. If it is silent, the line is flagged instead of given to both trades.
Are the two wages interchangeable?
No. May 2025 publishes different hourly means for equipment mechanics and for sheet metal workers.