United Kingdom tender estimating
Electrical Estimating Services for UK Commercial and Refurbishment Packages
UK electrical packages combine containment, cabling, devices and testing responsibilities that main contractors often issue as incomplete trade sets. F&K prepares remote electrical estimating takeoffs that reconcile layouts with schedules and keep client-supplied equipment visible before GBP rates are applied.
Remote estimating for United Kingdom projects. This page does not represent a local office.
Updated · F&K estimating methodology
Containment length is not the whole electrical story
A containment-only takeoff misses final circuit conductors, data pathways and emergency lighting that live on separate drawings. Refurbishment work adds isolation, temporary power and stripping of redundant circuits. F&K measures the electrical scope you are actually pricing and lists interfaces that appear to belong to the mechanical or main-contractor package.
Building regulations and Approved Documents cited for England, or the corresponding standards in the other nations, inform documentation but do not replace the issued electrical design. F&K does not perform design or BS 7671 certification; those remain with competent persons named on the project.
What the takeoff can include
Containment and cabling
Measure tray, basket, conduit and conductors by system where drawings support the routing and cable schedules.
Devices and luminaires
Count switches, sockets, detectors and lights against schedules and layouts, noting conflicts as queries.
Distribution equipment
List boards, isolators and equipment connections, flagging free-issue gear separately from contractor supply.
Testing and temporary works
Carry testing, commissioning and temporary power only when assigned to the electrical package.
Measurement and scope checks
Electrical measurement reconciles device schedules to layouts, then builds containment runs from the routing drawings. Refurbishment jobs maintain a strip-out register. GBP pricing uses your labour constants and material baskets after the quote locks system coverage. Open items stay visible until the design team answers, and no silent allowance is inserted to close a gap. Open items stay visible until the design team answers, and no silent allowance is inserted to close a gap. Open items stay visible until the design team answers, and no silent allowance is inserted to close a gap. Open items stay visible until the design team answers, and no silent allowance is inserted to close a gap. Open items stay visible until the design team answers, and no silent allowance is inserted to close a gap. Open items stay visible until the design team answers, and no silent allowance is inserted to close a gap.
Illustrative office floor device reconciliation
A CAT-B electrical package issues both a layout and a device schedule.
| Source | Count | Workbook action |
|---|---|---|
| Lighting layout | 84 luminaires | Base luminaire count by type. |
| Emergency schedule | 12 EM fittings | Twelve of the 84 carry emergency packs; packs listed separately. |
| Socket schedule | 110 outlets | Layout shows 104; six-outlet discrepancy raised as query. |
Illustrative only. Fire alarm and data often sit on separate drawings and may be excluded unless quoted.
Deliverable, pricing basis and quote
Electrical workbooks can support first-fix or second-fix packages. The quote states whether data, fire alarm and temporary power are included. Typical delivery is 24–48 hours from complete electrical drawings. Mid-tender drawing revisions reprice only the touched systems once agreed.
Explore our full electrical estimating services scopeQuestions about this scope
Can you exclude fire alarm and data?
Yes. Many UK electrical packages are power and lighting only.
Do you design cable sizes?
No. Conductor sizes are taken from the design documents.
How are client-supplied luminaires handled?
They are counted for installation only unless the quote adds supply.
Official project references
- GOV.UK guidance on the VAT domestic reverse charge for construction
Electrical subcontract pricing presentation may be affected; confirm with your tax adviser.