Dubai & UAE tender estimating
UAE BOQ and Quantity Takeoff Services for Fit-Out and Building Tenders
Send your Dubai or Abu Dhabi tender package for a measured bill of quantities or trade takeoff that keeps the consultant's item codes, metric units and addenda trail intact. F&K is a remote United States estimating team. We prepare editable workbooks for contractors who need a checkable measurement before pricing in dirhams, without claiming a UAE quantity-surveying practice or local office.
Remote estimating for United Arab Emirates projects. This page does not represent a local office.
Updated · F&K estimating methodology
Gulf BOQs still live or die on the named measurement method
Many UAE bills still cite Principles of Measurement International (POMI), while others name NRM 2, CESMM or a project preamble that overrides both. POMI was archived by RICS in March 2023, yet it remains binding wherever the contract names it. The practical risk is not the archive stamp — it is silent switching. If the tender says POMI and your rate library assumes NRM work-section coverage, working space, formwork or disposal can disappear into another item.
Fit-out packages add a second trap: landlord and tenant scope splits. A mall unit BOQ that mixes base-building chilled-water terminals with tenant ceilings will mislead every trade quote that follows. F&K keeps landlord works, tenant works, provisional sums and supplier-furnished equipment on separate lines, then marks which drawing issue produced each quantity so addenda can reprice only the touched items.
What the takeoff can include
Architectural and finishes takeoff
Measure partitions, ceilings, floor finishes, joinery and wet-area waterproofing by room or tenancy from the finish schedule and reflected ceiling plan, with voids and retained finishes identified.
Structural quantities
Separate concrete grades, formwork contact area and reinforcement by element when the structural set is part of the package, keeping cast-in embeds and construction joints visible.
MEP schedule reconciliation
Count equipment, terminals, containment and distribution against the services schedules, and flag base-building versus tenant responsibility where the work letter draws that line.
BOQ reconciliation workbook
Preserve consultant item numbers, report missing or duplicated quantities with drawing references, and isolate every addendum so the bid team can see what changed.
Measurement and scope checks
Intake confirms the measurement statement, currency basis in AED, VAT treatment and tender deadline with time zone. We build a drawing register, measure net quantities to the named rules, and keep preambles that deem temporary works or working space included as explicit assumptions rather than hidden mark-ups. Where the method is silent, the query list records the gap before pricing starts.
Illustrative Dubai tenancy BOQ reconciliation
A hypothetical office fit-out issues a consultant BOQ and a later ceiling addendum. Figures explain the check method only; they are not a client project.
| Bill item | Issued quantity | Workbook finding |
|---|---|---|
| Acoustic ceiling tiles | 980 m² on base issue | Addendum A adds 140 m² on level 12; revised measured total 1,120 m². |
| Diffusers tagged DT-2 | 28 each | Mechanical schedule shows 31; three terminals sit on landlord drawings and stay out of tenant lines. |
| Screed make-up | Provisional 1 lump sum | Broken into 86 m² of levelling from the floor finish schedule so the provisional can be compared. |
VAT at 5 percent stays off these lines and appears only as a separate summary row when a priced return is requested.
Deliverable, pricing basis and quote
The return is an editable Excel workbook with measured quantities, drawing references, assumptions and an addenda log. A priced AED estimate uses your rates or supplier quotations and shows VAT separately. The written quote confirms trades, format, fee and delivery date — typically 24–48 hours from a complete package — before measuring begins.
Explore our full quantity takeoff services scopeQuestions about this scope
Do you prepare BOQs to POMI by default?
Only when the tender names POMI or you instruct us to use it. Otherwise the workbook follows the measurement statement in the documents, including NRM, CESMM or a bespoke preamble.
Is UAE VAT included in the quantities?
No. Quantities are measured exclusive of tax. When pricing is included, 5 percent VAT is shown as a separate summary line unless your written quote states another presentation.
Are you based in Dubai?
No. F&K measures remotely from the United States and returns a workbook your bid team can check. There is no UAE office or local QS accreditation claim.
Official project references
- Dubai Municipality — Dubai Building Code
Official code reference for Dubai projects. The tender documents still govern measurement and permit basis.