Canada tender estimating
Canada Quantity Takeoff Services for Multi-Unit and Commercial Bids
Canadian bids mix metric drawings, imperial habits and provincial tax rules that punish buried assumptions. F&K prepares remote quantity takeoffs in Canadian dollars for general contractors and trade bidders, with units and tax lines stated explicitly and no claim of CIQS membership.
Remote estimating for Canada projects. This page does not represent a local office.
Updated · F&K estimating methodology
Provincial code adoption changes the documents, not the arithmetic
The National Building Code is a model; provinces adopt on their own schedules with amendments. Ontario's current code path differs from provinces that have moved faster to newer NBC editions. The takeoff follows the edition your tender and permit cite. Municipal overlays such as energy step requirements can add envelope or mechanical items that must stay visible.
CCDC stipulated-price work leaves little room for missing quantities. Bid depositories in some provinces close trade bids days before the prime close. F&K sets delivery against the closing clock you name, including time zone, so a MERX or Biddingo deadline is not treated like a casual internal queue.
What the takeoff can include
Architectural and finishes quantities
Measure partitions, ceilings and finishes by suite type or zone, with rated assemblies identified.
Structural quantities
Separate concrete, steel and related structural items by level when those trades are included.
MEP quantities
Carry mechanical, electrical and plumbing counts with parkade and in-suite splits where relevant.
Tax-ready workbook structure
Keep measured scope exclusive of tax; GST, HST, PST or QST appear only on priced summary lines by province.
Measurement and scope checks
Intake captures municipality, province, units required and bid-close time. The workbook can follow CIQS elemental groups, CSI divisions or the employer's form. Dual-unit lines state the conversion basis instead of assuming one system. CAD rates come from your quotations. The workbook also records open clarifications so a missing detail does not silently become a firm quantity. Where freight, customs or mobilisation affect industrial cash flow more than measured units, those cost inputs stay outside the quantity columns until you provide a quotation basis.
Illustrative suite-type partition rollup
A mid-rise residential tender repeats two suite types plus corridors.
| Zone | Partition basis | Result |
|---|---|---|
| Type A suites | 18 × 48 m² | 864 m² partitions. |
| Type B suites | 10 × 71 m² | 710 m² partitions. |
| Corridors and shafts | 286 m² + 196 m² shaft wall | 482 m² shared assemblies listed apart. |
Illustrative multi-unit logic only. Fire ratings and board layers would be broken out on a live takeoff.
Deliverable, pricing basis and quote
Quantity workbooks issue in the format your bid form expects, with CAD pricing optional and taxes separate. Typical turnaround is 24–48 hours from a complete set. The written quote confirms trades, units and delivery against the tender clock. Revision rounds after addenda reprice only the affected lines, and the fee for those rounds is confirmed before remeasurement starts.
Explore our full quantity takeoff services scopeQuestions about this scope
Can you format to CIQS elemental headings?
Yes, when requested. F&K is not a CIQS member firm and claims no PQS designation.
Do you mix metric and imperial?
When the tender does. Each line states its unit basis.
Are taxes included in quantities?
No. Taxes appear only on priced summaries at the provincial treatment you confirm with your accountant.
Can the workbook stay quantities-only through tender?
Yes. Many bid teams apply their own rates locally. Quantities-only delivery still includes assumptions, drawing references and an addenda log.