A concrete takeoff example shows you exactly what a quantity takeoff produces: an Excel sheet with measured quantities, and a PDF with color-coded markups that trace every number back to a drawing. This guide walks through a concrete takeoff sample step by step. It shows the slab, footing, rebar, and formwork lines, explains how to read the sheet, and covers what the example leaves out. If you need the same deliverable for your own drawings, F&K Estimatings runs quantity takeoffs for single-trade and multi-trade packages.
The takeoff is the measuring stage of construction estimating. No pricing, no labor rates, no markup. Just quantities you can check line by line.
What a construction takeoff includes (Excel quantity sheet, color-coded PDF markups, CSI MasterFormat)
A professional takeoff ships as two linked files.
The Excel quantity sheet lists every item with its dimensions, calculation, quantity, and unit of measure. Each row carries a CSI MasterFormat code so the numbers slot into a bill of quantities (BOQ) without rework. Concrete sits in Division 03. Formwork, reinforcement, and accessories get their own line items under that division.
The marked-up PDFs are the audit trail. The estimator colors each measurement on the plan: slabs in one color, footings in another, rebar zones in a third. You can open any Excel row, find the matching markup, and check the dimensions yourself.
Software matters here. PlanSwift and Bluebeam Revu let the estimator measure digitally, keep a revision history, and export clean sheets. The deliverable is a concrete takeoff worksheet you can verify, not a black-box total.
A full package typically covers:
- Concrete volume by element (slabs, footings, walls, columns, beams)
- Formwork area by contact surface
- Rebar by bar size and spacing, converted to weight
- Waste factor per line, stated openly
- CSI MasterFormat codes on every row
A concrete takeoff example (illustrative quantities)
Here is a made-up concrete takeoff calculation example. It is hypothetical, not a real client project, and the numbers are rounded for clarity.
The scenario: a 40 ft × 60 ft slab-on-grade, 5 in thick, with a simple #4 rebar grid at 18 in on center each way, and a thickened edge footing.
Step 1: Slab area. 40 × 60 = 2,400 sq ft.
Step 2: Volume in cubic yards. 2,400 × (5 ÷ 12) = 1,000 cu ft. Divide by 27: 37.04 CY.
Step 3: Waste factor. A 5% allowance adds 1.85 CY. Order quantity: 38.9 CY, rounded to 39 CY. Waste-factor calibration matters on small pours because ready-mix concrete comes in full yards, and short loads cost more per yard.
Step 4: Rebar. Grid at 18 in o.c. each way: 2,400 ÷ 1.5 ≈ 1,600 linear ft per direction, 3,200 linear ft total. Add 10% for laps and waste: 3,520 ft. #4 bar weighs about 0.668 lb/ft, so roughly 2,351 lb, or 1.18 tons.
Step 5: Formwork. Perimeter is 200 linear ft. At 5 in depth, edge forms cover 200 × (5 ÷ 12) ≈ 83 sq ft of contact area.
| Item | Calculation | Quantity | Unit |
|---|---|---|---|
| Slab concrete | 2,400 sq ft × 5/12 ÷ 27 | 37.04 | CY |
| Waste (5%) | 37.04 × 0.05 | 1.85 | CY |
| Order quantity | 37.04 + 1.85 | 38.9 (round to 39) | CY |
| #4 rebar @ 18” o.c. | 3,200 lf + 10% laps | 3,520 | lf |
| Rebar weight | 3,520 × 0.668 | ~2,351 (1.18) | lb (tons) |
| Edge formwork | 200 lf × 5/12 | ~83 | sq ft |
That is the core of a concrete slab takeoff example. A footing takeoff example follows the same logic: length × width × depth per footing type, counted from the foundation plan, then rebar per footing schedule.
On a real project the sheet grows: column takeoffs, wall takeoffs, beam takeoffs, post-tension anchor counts, MEP sleeve penetration counts, and fire-rated joint quantities all get their own rows. A footing takeoff on a commercial job may run dozens of footing types with a bar-bending schedule crossover to confirm rebar weights.
How to read the Excel sheet and the marked-up PDFs
Open the Excel sheet first. Each row should answer four questions: what element, what dimensions, what calculation, what unit. If a row says “concrete, 37 CY” with no dimensions, the takeoff is not auditable. Push back.
Then open the PDF markup beside it. Find the color for the element you are checking. The measured area or length should match the Excel dimensions. On a slab takeoff, confirm the thickness noted in the markup matches the volume math.
Check the waste factor lines. They should be visible, not buried in a total. Check that rebar spacing on the sheet matches the structural drawings, and that lap allowances appear as a separate percentage.
A good quantity takeoff sample pdf reads like a math worksheet a stranger could redo. That is the test.
What this example does not include
The slab example above is deliberately small. A real concrete takeoff also covers items this one skips:
- Excavation and spoil reconciliation. Cut volumes, haul-off, and backfill are separate lines, often in Division 31.
- Base course and vapor barrier. Granular base in tons or CY, membrane in sq ft with lap.
- Elevator pit waterproofing and below-grade walls. These change formwork and waterproofing quantities.
- Podium slab transfer beams and tilt-up panel embeds. Common in commercial material takeoffs, and they add embedded plates, inserts, and connection counts.
- Winter pour curing allowances. Cold-weather protection is a cost line that depends on schedule, not just geometry.
- Phased pour sequencing. Pour joints split a slab into multiple placements, each with its own waste and formwork.
- Seismic tie spacing. In high-seismic areas, tie spacing tightens and rebar weight rises.
- Curtain wall mullion tally and cold-formed steel ledger. Adjacent trades that interface with the concrete edge.
- Revision-cycle quantity drift. When drawings revise, quantities move. A takeoff without a revision log hides that drift.
The example also excludes pricing. Quantities only. It is not a priced estimate, and it is not a substitute for a structural review.
How this relates to the sample PDF
The sample on the site shows the actual format F&K Estimatings delivers: the Excel quantity sheet layout, the CSI coding, and the color-coded PDF markup style. Where this article uses a hypothetical slab to teach the math, the concrete takeoff sample shows the real deliverable structure you would receive. Browse the rest of the samples library to see other trades and formats.
Use both together. Read this guide to understand the logic. Open the sample to see the output.
When to request a takeoff from your own drawings
Request a takeoff when you have drawings and need quantities you can bid from, check a subcontractor’s numbers against, or hand to an estimator. Typical triggers:
A bid deadline is close and your estimator is backed up.
You received a quote from a concrete sub and want a second set of quantities before signing.
You are comparing two design options and need volumes for each.
You need a material take off sample format that matches your cost codes.
You want a rebar takeoff sample to verify a supplier’s bar list.
If you are still learning the methods behind the sheet, the quantity takeoff methods guide and the material takeoff guide cover the underlying process. For Division 03 specifics, see the CSI Division 3 concrete guide. And if concrete is your whole scope, the concrete estimating services page covers that trade directly.
How it works: send plans, written quote (scope, fee, date), takeoff in PlanSwift / Bluebeam Revu, delivery
The workflow is short.
Send plans. Email drawings and specs to info@fandkestimatings.us, or call +1 (317) 751-5969. PDF plans are fine. Include any addenda.
Written quote. After document review you get a quote in writing: scope, fee, and delivery date. No verbal guesses.
Takeoff. The estimator measures in PlanSwift or Bluebeam Revu, codes each line to CSI MasterFormat, and builds the Excel sheet with matching PDF markups.
Delivery. You receive the Excel quantity sheet plus color-coded marked-up PDFs. If you use a template or cost codes, say so up front and the sheet is built to match.
Pricing and turnaround
Published tiers give you a working range before you send anything:
| Package | Typical fee | Typical turnaround |
|---|---|---|
| Small single-trade takeoff | $150–$400 | 24–48 hours after approval |
| Mid-size single-trade priced estimate | $400–$900 | 24–48 hours after approval |
| Multi-trade package | $900–$2,500 | 3–5 business days |
| Industrial and heavy civil | $1,000–$5,000+ | 4–7 business days |
| Ongoing estimating support | $1,800 per month | Ongoing |
Most single-trade work lands in 24–48 hours after approval. The written quote after document review confirms the exact fee and delivery date for your project. See the pricing page for the full tier list.
FAQs
What does a concrete takeoff example include?
Concrete volume by element in cubic yards, formwork contact area, rebar by size and spacing converted to weight, waste factors, and CSI MasterFormat codes. Delivered as an Excel quantity sheet plus color-coded marked-up PDFs.
Is this a real client project?
No. The 40 ft × 60 ft slab in this article is hypothetical and labeled as such. It exists to show the math. The sample PDF on the site shows the real deliverable format.
Do you also provide a sample PDF?
Yes. The concrete takeoff sample PDF shows the sheet layout and markup style. More formats are in the samples library.
Do you deliver quantities only, or priced estimates too?
Both. Takeoffs are quantities only. Priced estimates add material, labor, and unit costs. Say which you need when you send drawings, and the written quote states the scope.
What format do I receive (Excel, PDF markups, my template or cost codes)?
Standard delivery is an Excel quantity sheet plus color-coded marked-up PDFs. If you have a template or cost codes, send them with the plans and the sheet is built to match.
How do I get a takeoff from my own drawings?
Email plans to info@fandkestimatings.us or call +1 (317) 751-5969. You get a written quote with scope, fee, and delivery date after document review. Most single-trade work delivers in 24–48 hours after approval.
See the sample format, then send your drawings to info@fandkestimatings.us for a written takeoff quote.