Wall sections · Grout as drawn · No guessed edition
Las Vegas block and brick quantities follow the wall sections, and a missing code year does not change the piece count
Block and brick on a Las Vegas set are counted from the wall elevations and the sections. Nevada’s lack of a statewide private code does not change a block count. A fire rating or a grout note changes the count only when these sheets print that note. If the sheets never name an edition, the pieces stay as drawn and the edition cell stays empty. City of Las Vegas, Henderson, and county sheets are not mixed into one wall total.
CMU is square feet or block counts by the unit the elevation uses, and the choice is written down. Brick veneer is area of the wythe the section draws. Grout and rebar are the cells the section fills, not every cell. A bond beam is linear where the section shows the beam. Control joints are lengths. Flashings at the base of the veneer are lengths only where the detail draws them. Heat does not add a flashing course.
Series OEUM002982000000047202103 reports $28.02 an hour for Brickmasons and Blockmasons. The survey name places Henderson beside the city and places North Las Vegas there too. One published title covers both materials. The figure is not a brick price, not a block price, and not dollars per square foot. Covered public work over the January 2023 figure of $100,000 uses the project schedule. A private wall under that line does not.
Scaffold is a means note only when you ask for means. Stone accents are counted only on the elevations that show stone. A Henderson veneer detail is not applied to a city wall. The file lists masonry areas, the grout note as drawn, the authority line, and anything still open.
A screen wall at a Las Vegas porte-cochere is its own area, not the building veneer. Pilasters are each when the plan marks them. Lintels in the bond beam are lengths. Weep holes are counts only where the detail spaces them. Stone caps are lengths. A garden wall on a site plan is site masonry and stays out of the building total unless the bid form pulls it in. Henderson veneer is not applied here. Heat does not insert an extra wythe.
The City of Las Vegas has adopted the 2024 International Building Code — Ordinance 6910, adopted 16 July 2025, succeeding the 2021 edition adopted in September 2022 — and the city's own adoption history is the record to check. That adoption is the city's, not the valley's: Henderson and unincorporated Clark County adopt separately, and a set drawn under an earlier edition is priced against the edition it names. The wall sections still govern the piece count; the code note records which book the drawings cite.
The quantities in a masonry takeoff go past the wall area. CMU and brick are measured by area and by unit count, and the opening deduction basis is stated before either is extended: a wall with 2,400 square feet gross and 240 square feet of openings has 2,160 square feet net under that stated basis, and a different basis gives a different net. Mortar is a bag quantity from the unit count, grout is cubic yards from the filled cells, and bond beams are linear feet. Ties and anchors, lintels, sills, flashing and weeps are counted where the details draw them — a net wall area alone does not quantify them.
Reinforcing follows the structural notes and the sections. Vertical bars are lengths by size from the wall schedule, horizontal joint reinforcing is linear where the spec calls it, and grout fills only the cells the section fills — a fully grouted wall and a partially grouted wall are different cubic yards, and the takeoff says which one the section shows. Control joints are lengths, and a joint the drawings never locate stays unresolved rather than being spaced by habit. Stone caps and cast-stone accents are lengths and counts from the elevations that show them.
Commercial masonry in Las Vegas is the same measurement applied to larger walls: CMU backup behind a storefront, a veneer wythe on a retail shell, fire-rated shaft walls, stair towers and screen walls at a porte-cochere. Each wall type stays on its own line, because a shaft wall grouted solid and a veneer wythe grouted at intervals are not the same grout. Site masonry — a garden wall, a trash-enclosure wall, a monument sign base — stays out of the building total unless the bid form pulls it in. Scaffolding is a means note only when you ask for means, and it is priced from the heights the elevations show, not from a floor count.
Send the wall elevations, the sections, the structural masonry notes and the specification, with the bid form and its alternates. The file that comes back lists the masonry areas, the unit counts, the grout note as drawn, the authority line and anything still open. To talk through the scope before sending the set, call +1 (317) 751-5969.
Masonry quantities before guessing a Las Vegas grout rule
Las Vegas masonry questions
Do you grout every cell?
No. Grout follows the cells the wall section fills. A silent section leaves grout unresolved.
Is $28.02 a block price?
No. OEUM002982000000047202103 is the hourly statistic for Brickmasons and Blockmasons.
Which city’s wall detail is used?
The detail in this set. A Henderson sheet is not applied to a City of Las Vegas wall.
Which building code edition applies to a City of Las Vegas wall?
The City of Las Vegas adopted the 2024 International Building Code by Ordinance 6910 on 16 July 2025. The takeoff still uses the edition the drawings name, and Henderson and Clark County adopt separately.
How are window and door openings deducted?
The deduction basis is stated first, then the net area is extended from it. A 2,400-square-foot wall with 240 square feet of openings is 2,160 square feet net under that basis.