How to Estimate Construction General Conditions

By Published Updated

Have a contractor bid to prepare?

Request a Project Quote

Tell us the trades, project location and bid deadline. Choose quantities only, a priced estimate or a review of an existing workbook.

Drawings are optional for this enquiry. The written proposal confirms scope, fee and delivery after review.

Inspect sample deliverables

Continue reading the article ↓

Request a quote for paid estimating or quantity takeoff services. Share your trade scope, project location and bid deadline. We confirm the fee and deliverables before work starts. Fields marked * are required.

Contact and project details
Choose your phone country and enter your local number. Or enter a full number starting with + and its country code, regardless of the country selected.

Project Drawings (optional)

PDF, CAD/BIM, Office, ZIP or image documents. Up to 5 files, 25 MB each; account limits also apply.

No drawings attached. This field is optional.

    Already have a sharing link? Paste it here instead of uploading. Grant access to info@fandkestimatings.us; do not include passwords.

    Upload only documents you are authorized to share. Privacy policy. This request does not opt you into marketing messages.

    Prefer to discuss the scope first, or having trouble with the form? Email your project details or discuss your project on WhatsApp. Include your project location, trade scope and bid deadline.

    General conditions (GCs), often called jobsite overhead, are the costs of running a project that do not belong to any one trade: supervision, the field office, temporary facilities, cleanup, and the administrative work of getting a building built and closed out. Because they are spread across the whole job, they are easy to underestimate, and because many of them are tied to time, they grow every week a project runs long.

    This post explains how to classify GC items, builds an illustrative GC budget, and shows how the same schedule can help quantify a possible delay-related cost. Whether any extension is recoverable depends on the contract, contemporaneous records and professional review. For a condensed reference, see our general conditions guide.

    General Conditions vs. General Requirements vs. Overhead

    These terms get mixed up, so it helps to separate them:

    • General requirements are the specification sections in CSI MasterFormat Division 01 (01 General Requirements). They describe administrative and temporary-facility obligations such as submittals, quality control, temporary facilities and closeout.
    • General conditions is the cost category the estimator builds to satisfy those requirements and run the site. In AIA contracts, “General Conditions” is also the name of the contract document (A201), which is a different thing again.
    • Home office overhead covers the company’s costs that are not tied to one project: office rent, executives, accounting, estimating staff. It is usually carried as a separate markup, not in GCs.

    Keep home office overhead out of the GC estimate. Mixing the two makes it hard to defend either number in a change order or claim.

    Three Ways GC Items Behave

    The most useful way to estimate GCs is by cost driver.

    Driver How to price Typical items
    Time-based Monthly (or weekly) rate x duration Superintendent, project manager, project engineer, field office rental, temporary power usage, toilets, vehicles, internet
    Fixed / lump sum One-time cost regardless of duration Trailer delivery and removal, project sign, temporary fence installation, final cleaning, as-builts and O&M manuals
    Quantity-based Quantity x unit rate Dumpster pulls, testing (per cylinder set or per inspection visit), temporary protection per SF, final clean per SF

    Some items straddle categories. Dumpster service, for example, depends on how much demolition and packaging waste the trades generate, not just the calendar. Bonds and builder’s risk insurance are usually priced as a percentage of contract value and are often carried below the line with markups rather than in GCs; decide which your company does and be consistent.

    Worked Example: A 10-Month GC Budget

    Example: a 60,000 SF, 10-month commercial interior and core project with an estimated direct cost of $6,200,000. All rates are illustrative 2026 figures and include labor burden where applicable. Use your own payroll costs and local vendor quotes.

    Time-based items

    Item Monthly rate Months Cost
    Project manager (50% allocated: $14,000 x 0.5) $7,000 10 $70,000
    Superintendent (full-time, includes closeout) $16,500 10.5 $173,250
    Project engineer $9,500 9 $85,500
    Field office trailer rental $950 10 $9,500
    Temporary toilets (3 units x $175) $525 10 $5,250
    Temporary power usage $1,200 10 $12,000
    Superintendent vehicle $1,100 10 $11,000
    Time-based subtotal $366,500

    Arithmetic check: $70,000 + $173,250 + $85,500 + $9,500 + $5,250 + $12,000 + $11,000 = $366,500.

    The superintendent runs half a month past substantial completion for punch list and closeout; the project engineer starts after mobilization, so both carry durations different from the 10-month schedule.

    Fixed and quantity-based items

    Item Basis Cost
    Dumpster pulls 6 pulls/month x $550 x 10 months $33,000
    Trailer delivery, setup and removal Lump sum $2,400
    Temporary fence 1,400 LF x $4.50/LF $6,300
    Final cleaning 60,000 SF x $0.35/SF $21,000
    Project sign Lump sum $1,500
    Closeout documents and as-builts Lump sum $3,000
    Subtotal $67,200

    Arithmetic check: $33,000 + $2,400 + $6,300 + $21,000 + $1,500 + $3,000 = $67,200.

    Total and percentage

    • Total GCs = $366,500 + $67,200 = $433,700
    • GCs as a percentage of direct cost = $433,700 / $6,200,000 = 7.0%

    A percentage is a useful sanity check against your own past jobs, but it should be the result of the build-up, not the starting point. A short, dense project and a long, slow one with the same direct cost can have very different GC percentages.

    What a delay costs

    The monthly run rate of the time-based items at full staffing is:

    $7,000 + $16,500 + $9,500 + $950 + $525 + $1,200 + $1,100 = $36,775/month

    If the schedule extends two months, an illustrative additional two months at this assumed full-staffing rate is $36,775 x 2 = $73,550, before any contract-permitted markup. This is a cost scenario, not an entitlement or certified delay claim; actual staffing, mitigation, contract clauses and contemporaneous records may change the result. This is why a time-based GC schedule, priced by month, is far easier to use in a change order than a single lump-sum GC line. Our change order pricing guide covers how to present that cost.

    What Else Belongs in GCs

    Check the Division 01 sections and the contract for items such as:

    • Survey and layout, if not carried by a trade
    • Temporary heat, enclosure and weather protection
    • Safety program costs: site-specific safety plan, first aid, fall protection not provided by subs
    • Hoisting or shared equipment, such as a forklift or telehandler used by several trades
    • Testing and special inspections the contractor is required to pay for
    • Scheduling software, document control and project photography
    • Winter conditions, dewatering or traffic control where not in a trade scope
    • Permits and fees, if the contract assigns them to the contractor

    Checklist

    • Schedule reviewed and a realistic duration used, including closeout
    • Each staff position priced at burdened monthly cost with its own start and end dates
    • Items classified as time-based, fixed or quantity-based
    • Division 01 sections read line by line and compared to the GC list
    • Items carried by subcontractors excluded from GCs (and confirmed during bid leveling)
    • Home office overhead, bonds and insurance handled consistently outside or inside GCs
    • Monthly run rate calculated for use in delay and change pricing
    • GC percentage compared to similar past projects as a final check

    Common Mistakes

    • Using a flat percentage instead of a time-based build-up.
    • Pricing the schedule the owner wants rather than the one the work requires.
    • Leaving out closeout time. Supervision and the trailer do not stop at substantial completion.
    • Double carrying items such as dumpsters, hoisting or temporary protection that subs already include.
    • Forgetting burden on field staff salaries. See our labor burden post.
    • Missing Division 01 requirements like mock-ups, commissioning support or extended warranty administration.

    How F&K Estimatings Can Help

    A general conditions schedule can be prepared from the project duration, staffing assumptions and scope documents agreed for the estimate. Ask for those assumptions to be stated in the written deliverables so you can review schedule changes. This is part of our construction estimating services. See pricing for a quote on your next bid.

    Bid-Risk Management

    Ready to Improve Your Estimating Accuracy?

    Send your drawings for a written quote on a takeoff or estimate, after document review.

    Send drawings for a written quote

    Include trades, location and bid deadline. We confirm fee and delivery before work starts.

    Request a quote for paid estimating or quantity takeoff services. Share your trade scope, project location and bid deadline. We confirm the fee and deliverables before work starts. Fields marked * are required.

    Contact and project details
    Choose your phone country and enter your local number. Or enter a full number starting with + and its country code, regardless of the country selected.

    Project Drawings (optional)

    PDF, CAD/BIM, Office, ZIP or image documents. Up to 5 files, 25 MB each; account limits also apply.

    No drawings attached. This field is optional.

      Already have a sharing link? Paste it here instead of uploading. Grant access to info@fandkestimatings.us; do not include passwords.

      Upload only documents you are authorized to share. Privacy policy. This request does not opt you into marketing messages.

      Prefer to discuss the scope first, or having trouble with the form? Email your project details or discuss your project on WhatsApp. Include your project location, trade scope and bid deadline.